Community
Leisure
Sport

Leyton Leisure Centre

October 2013

Within a tight budget the SPACE & PLACE project team took the existing Leyton Leisure Lagoon (rebranded as the ’Leyton Leisure Centre’) to create a new centre with facilities that match the demands of the centre’s users, in particular, the need for families and children.

The refurbishment works included:

  • Upgrading the external façade with render and rainscreen cladding to lift the dated brickwork
  • A new entrance canopy
  • A new flume ride relocated from the front of the building to the back with its own dedicated Aquacatch
  • Converting the existing leisure pool and redundant ’dangerous’ rapids into a 25 metre community pool and altering the depth

The project was successfully completed in October 2013, costing £3.5m